Advice 25-015––Schedule 401––Service to New Large Energy Use Facilities
Tariff Proceeding
Filed
Overview
PacifiCorp proposes a new tariff (Schedule 401) establishing a distinct customer class for new Large Energy Use Facilities (primarily data centers $\ge$20 MW).
Key Details
Docket Number
ADV 1790 / UE 463
Regulatory Body
Public Utility Commission of Oregon
Filing Date
Thu Dec 31 2026 12:00:00 GMT+0000 (Coordinated Universal Time)
Current Status
Filed
Technical Details
Utility:
PacifiCorp d/b/a Pacific Power
RTO / ISO:
Customer Class
New Large Energy Use Facilities (Schedule 401)
Load Threshold
20 MW
Contract Term
10+ years
Financial Security
Agreements may contain unique credit, deposit and security provisions
Exit Fees
20 MW
Curtailment Terms
20 MW
Cost Allocation Provisions
20 MW