Applications for Reconsideration and Rehearing and Motions for Clarification Granted in Part and Denied in Part

Tariff Proceeding

Closed

Overview

This OPUC order responds to applications for reconsideration regarding a new tariff (Schedule 96) for large data centers, addressing cost allocation, a 30-year maximum contract term, exit fees, minimum demand charges, and interconnection queue rules to prevent unwarranted cost-shifting.

Key Details
Docket Number

UM 2377

Regulatory Body

Public Utility Commission of Oregon

Filing Date

Mon Aug 31 2026 12:00:00 GMT+0000 (Coordinated Universal Time)

Current Status

Closed

Technical Details
Utility:

Portland General Electric Company

RTO / ISO:
Customer Class

Data Centers (Schedule 96) and Large Load Customers (Schedules 89 and 90)

Load Threshold

20 MW (trigger for Schedule 96)

Contract Term

Min. 10 years for 20 MW load, increasing by one year for each 10 MW increment, capped at a maximum of 30 years for loads 220 MW or greater

Financial Security

Deposits used to deter overestimated demand

Exit Fees

20 MW (trigger for Schedule 96)

Curtailment Terms

20 MW (trigger for Schedule 96)

Cost Allocation Provisions

20 MW (trigger for Schedule 96)

None specified