POWER & REGULATION

New Large Data Center Load Policy

Tariff Proceeding

Under Review

Overview

Seattle enacted Ordinance 127473, establishing retail rate schedules and a new customer class and service conditions for data centers whose demand constitutes a New Large Load.

Key Details
Docket Number

2026 proposed rate ordinance

Regulatory Body

Washington Utilities and Transportation Commission

Filing Date

Fri Aug 21 2026 12:00:00 GMT+0000 (Coordinated Universal Time)

Current Status

Under Review

Technical Details
Utility:

Seattle City Light

RTO / ISO:
Customer Class

New or expanded data centers meeting Seattle City Light's New Large Load criteria

Load Threshold

10 MVA threshold for the new data-center large-load policy. The separate land-use moratorium uses 20 MVA and should not be entered in this utility-rate record.

Contract Term

Customer-specific service agreement for the life of the service arrangement; no universal number of years verified in the public ordinance record.

Financial Security

Customer must enter a service agreement accepting responsibility for infrastructure and related costs over the service arrangement; no universal security amount verified.

Exit Fees

10 MVA threshold for the new data-center large-load policy. The separate land-use moratorium uses 20 MVA and should not be entered in this utility-rate record.

Curtailment Terms

10 MVA threshold for the new data-center large-load policy. The separate land-use moratorium uses 20 MVA and should not be entered in this utility-rate record.

Cost Allocation Provisions

10 MVA threshold for the new data-center large-load policy. The separate land-use moratorium uses 20 MVA and should not be entered in this utility-rate record.

​

Source & Documents
View the official document and related materials for this proceeding.