POWER & REGULATION

Data-center load-growth limits

Other

Under Review

Overview

Grant PUD imposed customer-specific limits on future data-center load growth to protect reliability while transmission upgrades are completed. The March 2025 official recap describes the planned limits, and an August 2025 recap confirms that limits had been imposed.

Key Details
Docket Number

Commission action 2025-03-25

Regulatory Body

Washington Utilities and Transportation Commission

Filing Date

​

Current Status

Under Review

Technical Details
Utility:

Grant County PUD

RTO / ISO:
Customer Class

Existing data-center customers; similar limits may extend to other industrial customers whose growth creates reliability risk

Load Threshold

Customer-specific remaining-growth limits are communicated directly to each data-center customer; no uniform public MW threshold was stated.

Contract Term

Interim reliability measure with no fixed public expiration date; limits may be raised as upgrades permit.

Financial Security

Not Applicable — no financial-security term identified.

Exit Fees

Customer-specific remaining-growth limits are communicated directly to each data-center customer; no uniform public MW threshold was stated.

Curtailment Terms

Customer-specific remaining-growth limits are communicated directly to each data-center customer; no uniform public MW threshold was stated.

Cost Allocation Provisions

Customer-specific remaining-growth limits are communicated directly to each data-center customer; no uniform public MW threshold was stated.

​