Temporary Moratorium on Large Data Centers

Greensboro, NC

Action Status

Effective

Policy Type

Moratorium

Government Level

Local

Legal Mechanism

Ordinance

Action Overview

Temporary Moratorium on Large Data Centers

Jurisdiction

Greensboro, NC

Local

City Council

Data-center moratorium ordinance adopted 2026-08-18

8/18/26

Ordinance

Effective

Policy Name

Government Level

Government Body

Official Identifier

Adoption Date

Legal Mechanism

Action Status

Description

The City Council adopted a temporary moratorium on development applications for large data centers while staff prepares permanent amendments to the Land Development Ordinance. The moratorium applies to facilities with an electrical demand greater than 10 megawatts and is intended to provide time to evaluate infrastructure, utility, environmental, and land-use impacts before establishing permanent development standards.

Moratorium Details 

Moratorium Description

Acceptance, processing, and approval of development applications for qualifying data centers with an electrical demand greater than 10 MW.

Actions Paused

Acceptance, processing, and approval of development applications for qualifying data centers with an electrical demand greater than 10 MW.

Required Work

Conduct technical review of infrastructure, electric grid capacity, utility service, environmental impacts, land use compatibility, and best practices; hold work sessions; prepare amendments to the Land Development Ordinance regulating data centers.

Duration

184

days

Days Left

140

days

Source

View the official document for this government action